Moving the 500 kV Egkh “Imereti” N295 mast from the landslide-prone zone

In the summer of 2011, the precipitations that came to Western Georgia and the developed landslides in the area surrounding Shukeri village of Orpiri community of Tkibuli municipality threatened the stability of the 500 kV power station “Imereti” U2+5 type N295 mast.

Based on the study of the geological and geodetic condition of the place, a safe place for placing the said mast was selected and the project was developed together with “Energoxel Project” LLC.

The N295 mast of Egkh “Imereti” was moved to a safe place in the alignment of Egkh.

Other projects

Replacement of corroded insulators on 500 kV Egkh “Imeret”.

In connection with the switching of the double-chain 330 kV “1,2 Gardabani” on the Georgia-Azerbaijan border

Moving the 500 kV Egkh “Imereti” N295 mast from the landslide-prone zone

Conditions hindering the operation of power transmission lines

Replacement of damaged wires on the 500 kV EGH “Imeret” overhead power line

Moving the 500 kV Egkh “Imereti” N295 mast from the landslide-prone zone

This site is registered on wpml.org as a development site. Switch to a production site key to remove this banner.